28 January 2008

Steel Work Complete - Work starting on Cladding

Friday 25th January saw the completion of the steel structure. The major works in progress now are the cladding of the roof area and bricklaying to the foundations.

These pictures were taken last week from the air and show the full expanse of the building.


16 January 2008

Steel Work On Target



Despite the terrible weather of the last few weeks the steel workers, who have worked in some terrible conditions, are still on target to have the frame complete by the end of January. Today also saw the first of the cladding panels fitted to the roof.


07 January 2008

New Building Progress - Starting to Take Shape
Happy New Year to All. The steel structure is taking shape rapidly now. The new building can be seen from vantage points around the local area and is really looking impressive.