29 November 2007

New Building Progress - Steel Structure
Monday morning (26/11/07) saw the delivery of the first consignment of steel. The steel workers started immediately and the building is taking shape rapidly.

12 November 2007

New Building Progress - Groundworks

Finally after several delays due to the weather, archaeological finds and design changes the Groundworks for the new building have started. The entire site of 4 acres has undergone a Soil Stabilisation process, producing a hard crust on which the final finish will be laid.
At the moment the groundworkers are digging 115 foundation pits that will support the steel structure as well at the footings for the external walls.
This work is due to be completed by Wednesday 21st November, which is perfect timing for the steel work which arrives on Monday 26th November? Fingers crossed.

01 November 2007

JT8D-200 Tooling Delivery
Summit Aviation has now taken delivery of a full suite of JT8D-200 overhaul tooling. The tools arrived from Finland this week after the national airline completed their last JT8D rebuild. The tools are now going through an exhaustive check and reburbish process whist the company continue with the building of the new 100,000 sqft facility.
The company plan to be fully approved on the JT8D-200 in the new year following staff training.